What's happening?

The final stage of work is about to begin on Daleside Road to resurface the newly widened carriage way from Racecourse roundabout to Colwick village.

The road has been widened to accommodate a bus lane in both directions to speed up journey times east of the city and improvements have been made for pedestrians and cyclists.

How will this affect traffic?

Monday 12 February – 5 nights of work (7:30pm – 5am) to remove the existing road surface. This will involve a lane closure with two-way traffic lights in operation.

Monday 19 February – 5 days of off peak work (Monday 9:30am – 3pm and 7:30pm – 5am then Tuesday – Thursday (9:30am – 3:30pm), this will be completed outside of rush hour and scheduled during half term to reduce the effect on traffic.

Monday 26 February – 4 days to complete the final stage of resurfacing works (9:30am – 3:30pm) again completed outside of peak times.