Latest Updates

If programme works are affected by weather or other delays we will update you here.

Multiple Footway Improvements

Scheme Detail Footpath surface treatment programme (slurry seal)
Full list of roads available here under programme of works
Restrictions and Traffic Management No road closures will be in place. There will always be one footpath open for pedestrians
Start Date 16/01/23
Expected Duration 9 Weeks for the programme – each road will be of short duration, usually only one day. The largest schemes could take as long as a week.

This work is very dependent on weather: any roads affected by this will be deferred until a later date, at the end of the programme.

Contractor Colas
Latest Information Updated on 12/01/23 – Currently programmed

Morris Road

Scheme Detail Footway Improvements
Carriageway Resurfacing
Restrictions and Traffic Management No stopping for the full duration of works.

Traffic control for footway works.

Weekday closure for carriageway resurfacing.

Start Date 02/02/23 (Footway)
27/03/23 (Carriageway)
Expected Duration 7 weeks (Footway)
1 week (Carriageway)
Contractor Thomas Bow
Emergency Contact 0115 924 4555
Latest Information Updated on 13/02/23

Lindbridge Road

Scheme Detail Carriageway Resurfacing
Restrictions and Traffic Management No stopping for the full duration of works.

Traffic control for footway works.

Weekday closure for carriageway resurfacing.

Start Date 09/02/23 – Road closure starts on 20/02/23
Expected Duration 3 weeks
Contractor Thomas Bow
Emergency Contact 0115 924 4555
Latest Information Updated on 13/02/23

Tree Maintenance Work

Scheme Detail Major tree works on three key traffic routes – Lenton Boulevard, Castle Boulevard and Derby Road. More information on specific timings can be found here.
Restrictions and Traffic Management Some roads will be closed. People travelling through the area are being advised that delays are likely and they should consider using alternative routes if possible.
Start Date 20/02/23
Expected Duration 3 weeks – expected to end on 10/03/23. The work will be carried out during off-peak hours from 9am – 3pm, avoiding the morning and afternoon rush hours.
Latest Information Updated on 14/02/23 – Currently programmed