Across Nottingham
- Start: September 2022
- End: March 2024
Latest Updates
If programme works are affected by weather or other delays we will update you here.
Multiple Footway Improvements |
|
Scheme Detail | Footpath surface treatment programme (slurry seal) Full list of roads available here under programme of works |
Restrictions and Traffic Management | No road closures will be in place. There will always be one footpath open for pedestrians |
Start Date | 16/01/23 |
Expected Duration | 9 Weeks for the programme – each road will be of short duration, usually only one day. The largest schemes could take as long as a week.
This work is very dependent on weather: any roads affected by this will be deferred until a later date, at the end of the programme. |
Contractor | Colas |
Latest Information | Updated on 12/01/23 – Currently programmed |
Morris Road |
|
Scheme Detail | Footway Improvements Carriageway Resurfacing |
Restrictions and Traffic Management | No stopping for the full duration of works.
Traffic control for footway works. Weekday closure for carriageway resurfacing. |
Start Date | 02/02/23 (Footway) 27/03/23 (Carriageway) |
Expected Duration | 7 weeks (Footway) 1 week (Carriageway) |
Contractor | Thomas Bow |
Emergency Contact | 0115 924 4555 |
Latest Information | Updated on 13/02/23 |
Lindbridge Road |
|
Scheme Detail | Carriageway Resurfacing |
Restrictions and Traffic Management | No stopping for the full duration of works.
Traffic control for footway works. Weekday closure for carriageway resurfacing. |
Start Date | 09/02/23 – Road closure starts on 20/02/23 |
Expected Duration | 3 weeks |
Contractor | Thomas Bow |
Emergency Contact | 0115 924 4555 |
Latest Information | Updated on 13/02/23 |
Tree Maintenance Work |
|
Scheme Detail | Major tree works on three key traffic routes – Lenton Boulevard, Castle Boulevard and Derby Road. More information on specific timings can be found here. |
Restrictions and Traffic Management | Some roads will be closed. People travelling through the area are being advised that delays are likely and they should consider using alternative routes if possible. |
Start Date | 20/02/23 |
Expected Duration | 3 weeks – expected to end on 10/03/23. The work will be carried out during off-peak hours from 9am – 3pm, avoiding the morning and afternoon rush hours. |
Latest Information | Updated on 14/02/23 – Currently programmed |