Latest Updates

If programme works are affected by weather or other delays we will update you here.

Willow Road improvements

Scheme Detail Footway Improvements and Carriageway Resurfacing
Restrictions and Traffic Management No Stopping for full duration of works

Traffic control for Footway Works

Weeknight closure for Carriageway Resurfacing

Start Date 5/9/22 (Footway Improvements)

31/10/22 (Carriageway Resurfacing)

8/11/22-23/11/22 (Additional footway improvements)

Expected Duration 8 Weeks (Footway Improvements)

1 Week (Carriageway Resurfacing)

Contractor Thomas Bow
Emergency Contact 0115 924 4555
Latest Information 03/11/22 – Original works to be completed as planned. Further works are planned to provide additional improvements.

Parkdale Road

Scheme Detail Road Safety Scheme and Carriageway Resurfacing
Restrictions and Traffic Management No Stopping for full duration of works

Road closed to traffic – No Through Road, Resident Access only

Start Date 19/9/22
Expected Duration 8 Weeks
Contractor Thomas Bow
Emergency Contact 0115 924 4555
Latest Information 03/11/22 – Currently on site and on programme

Retreading Programme

Scheme Detail Retread is a cold in-situ recycling process which reconstructs the entire carriageway or footway surface to a depth of 75mm.
Restrictions and Traffic Management The work is completed in 2 phases roughly 2 weeks apart. Whilst the machinery is on site the road will be closed and access only maintained to residents. Roads will reopen when machinery is not present when possible.
Start Date Frinton Road – Phase 1 complete

Eltham Drive – Phase 1 completed by 11/11/22

Cope Street – Phase 2 only

Stoneleigh Street – 14/11/22 start date

Phase 2 to begin 14/12/22 with roughly 1 day per road

Expected Duration Works expected to fully complete end of December
Contractor Colas
Emergency Contact
Latest Information 03/11/22 – Works delayed due to poor weather and delayed phase 2 crew. Road to be fully reopened between phases.

Church Lane

Scheme Detail Footway Improvements and Carriageway Resurfacing
Restrictions and Traffic Management No stopping for full duration of works
Traffic control for Footway Works
Weekday closure for Carriageway Resurfacing
Start Date 02/11/22 (Footway Improvements)
14/11/22 (Carriageway Resurfacing)
Expected Duration 2 Weeks (Footway Improvements)
1 Week (Carriageway Resurfacing)
Contractor Thomas Bow
Emergency Contact 0115 924 4555
Latest Information 03/11/22 – Expected to start on time

Tettenbury Road

Scheme Detail Footway Improvements and Carriageway Resurfacing
Restrictions and Traffic Management No stopping for full duration of works
Traffic control for Footway Works
Weekday closure for Carriageway Resurfacing
Start Date 28/11/22 (Footway Improvements)
25/01/23 (Carriageway Resurfacing)
Expected Duration 8 Weeks (Footway Improvements)
1 Week (Carriageway Resurfacing)
Contractor Thomas Bow
Emergency Contact 0115 924 4555
Latest Information 03/11/22 – Expected to start on time but delayed from original start date