Street Weed Spraying

We are responsible for ensuring that verges along the roads and pavements we maintain meet safety standards. We carry out weed control throughout the year in the below phases.

There will be reduced chemical applications within the city’s parks and green spaces unless there is no other practical method of weed control, e.g. Japanese knotweed, sports turf weed control etc.

Phase 1

January – March, Winter Weed Clearance Programme

Each neighbourhood team will spend enough time to make sure that known weed hotspots—such as backlines, kerb lines, courtyards, and walkways on HRA land—are properly managed. This work will include strimming or scrapping out to ensure that moss, weeds and detritus are removed. With a good, robust sweeping routine, this work will help remove growing media and weed seeds, and should therefore help reduce the rapid growth of weeds in the spring.

Phase 2

March – April, Compressed Weed Spraying Programme

In the second phase of weed control, our teams will focus on supporting estate mowing across the city. This approach uses less petrol, which is better for the environment and gives the team more time to maintain the estates.

Phase 3

May – July, Spot Weed Programme

Phase 3 – We use a contractor for this phase which has a large team dedicated to complete the spray programme. This programme aims to get on top of the weed growth quickly in all areas of the city.

The second and third phase of weed spraying will visit all main artery roads and bus routes within each neighbourhood, and focus its main attention on areas with problem or persistent weed growth.

Phase 4

August – September, Spot Weed Programme

The final phase of weed spraying will be carried out by the end of August into late September. This phase will focus on going back and repeating the same spraying programme.


Weed Spraying Schedule 2025

LocationProgramme start dateStatusCompletion date
Clifton East13/05/2025Complete14/05/2025
Clifton WestComplete15/05/2025
Wollaton West17/05/2025Programmed
Lenton and Wollaton East21/05/2025In progress
Bilborough 23/05/2025Programmed
Leen Valley29/05/2025Programmed
Aspley02/06/2025Programmed
Radford02/06/2025Programmed
Basford04/06/2025Complete
Hyson Green and Arboretum05/06/2025Programmed
Berridge10/06/2025Programmed
Meadows16/06/2025Programmed
Castle Ward (City Centre)19/06/2025Programmed
Bulwell23/06/2025Programmed
Bulwell Forest25/06/2025Programmed
Bestwood27/06/2025Programmed
St Ann's30/06/2025Programmed
Sherwood (Mansfield Road only)01/07/2025Programmed
The Dales02/07/2025Programmed
Mapperley Park 03/07/2025Programmed

In the event of bad weather affecting the timescales indicated above, we’ll pause our services until the weather improves and it’s safe and effective to continue.

Acceptable level of weeds

In the images below, green represents ‘good’ while yellow represents ‘action is required’ and red represents ‘unacceptable’.

Related pages

WFP5394-Sherwood-Vale-21-1

Highways planned maintenance

Our transport teams will be making repairs to roads and cycle paths across all twenty wards to help improve traffic flow and safety.

Find out more
The-Ropewalk-2-e1559745850941-1024x775-1

Project information

More information on the different programmes and types of road treatment.

Find out more

Sign up to the transport newsletter

Roadworks bulletin every Friday
and monthly project updates.

Sign up for email updates

 

Enter your email address below to sign up for updates or to access your subscriber preferences.