List of schemes

WardRoadTypeInfoStart DateWork Stream
AspleyColeby RoadReconstructionIn DevelopmentTo Be ConfirmedLTP 25/26
AspleyDeepdene WayResurfaceComplete18/11/2024SfP 24/25
AspleyFenwick RoadResurfaceComplete20/01/2025SfP 24/25
AspleyLimetree AvenueResidents Parking Scheme Programmed 15/06/2025SfP 24/25
AspleyMaltby CloseResurfaceComplete13/01/2025SfP 24/25
AspleySherborne RoadReconstructionIn DevelopmentTo Be ConfirmedLTP 25/26
AspleyTiverton CloseFootway ResurfaceComplete13/01/2025SfP 24/25
AspleyWard wide Bin ReplacementComplete10/02/2025SfP 24/25
AspleyWard Wide Planned PatchingComplete01/02/2025SfP 24/25
AspleyWinsford CloseResurfaceComplete13/01/2025SfP 24/25
AspleyWithern RoadResurfacingIn DevelopmentTo Be ConfirmedLTP 25/26
BasfordAlpine StreetMicro AsphaltComplete09/04/2024LTP 24/25
BasfordBarlock RoadRetreadComplete08/04/2025LTP 25/26
BasfordBroadhurst AvenueResurfaceComplete21/01/2025SfP 24/25
BasfordBulwell LaneResurfaceProgrammed06/07/2025SfP 24/25
BasfordHeatherly DriveResurfaceComplete10/02/2025SfP 24/25
BasfordLlanberis GroveReconstructionProgrammed 25/07/2025LTP 25/26
BasfordMarlowe AvenueMicro AsphaltComplete07/06/2024LTP 24/25
BasfordMount PleasantMicro AsphaltComplete07/06/2024LTP 24/25
BasfordPark Lane 2 New Bollards Complete15/01/2025SfP 24/25
BasfordPercy StreetMicro AsphaltComplete10/04/2024LTP 24/25
BasfordStockhill LaneMicro AsphaltComplete11/04/2024LTP 24/25
BasfordWard Wide Parking RestrictionsIn DevelopmentSummer 2025SfP 24/25
BasfordWard Wide Bin ReplacementComplete17/02/2025SfP 24/25
BasfordWhitemoor RoadMicro AsphaltComplete08/04/2024LTP 24/25
Basford & SherwoodValley RoadMicro AsphaltComplete18/03/2025LTP 24/25
BerridgeArno AvenueMicro AsphaltComplete25/03/2025LTP 25/26
BerridgeEgypt RoadResurfaceComplete03/02/2025SfP 24/25
BerridgeExeter RoadResurfacingIn DevelopmentTo Be ConfirmedLTP 25/26
BerridgeGladstone StreetMicro AsphaltComplete07/04/2024LTP 24/25
BerridgeHadbury RoadResurfaceComplete24/02/2025SfP 24/25
BerridgeLamcote StreetMicro AsphaltComplete03/04/2024LTP 24/25
BerridgeMaxwell CloseMicro AsphaltComplete05/04/2024LTP 24/25
BerridgePremier RoadMicro AsphaltComplete07/04/2024LTP 24/25
BerridgeReigate RoadMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
BerridgeSecond AvenueMicro AsphaltComplete06/04/2024LTP 24/25
BerridgeSilverdale RoadMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
BerridgeSuez Street AreaDropped Crossing ImprovementsIn DevelopmentSummer 2025SfP 24/25
BerridgeWard Wide Parking RestrictionsIn DevelopmentSummer 2025SfP 24/25
BerridgeWimbledon Road AreaResident Parking Scheme and Parking RestrictionsIn DevelopmentSummer 2025SfP 24/25
BerridgeWiverton RoadMicro AsphaltComplete25/03/2025LTP 25/26
BestwoodB6004 Arnold RoadMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
BestwoodBeckhampton RoadReconstructionIn DevelopmentTo Be ConfirmedLTP 25/26
BestwoodCottam Drive / Cottam GardensMicro AsphaltComplete17/03/2025SfP 24/25
BestwoodElmbridgeMicro AsphaltComplete26/03/2025SfP 24/25
BestwoodLytham GardensMicro AsphaltComplete17/04/2024LTP 24/25
BestwoodMildenhall CrescentResurfaceComplete17/02/2025SfP 24/25
BestwoodSouthglade Road (Phase 2)ReconstructionProgrammed28/07/2025LTP 25/26
BestwoodSouthglade Road (Phase 1)ResurfaceProgrammed28/07/2025SfP 24/25
BestwoodWard Wide Planned PatchingComplete01/12/2024SfP 24/25
BestwoodWard Wide Bin ReplacementComplete24/02/2025SfP 24/25
BilboroughBracebridge DriveResurfacingProgrammed11/08/2025LTP 24/25
BilboroughBurnside RoadMicro AsphaltComplete24/03/2025SfP 24/25
BilboroughChingford RoadResurfaceProgrammed28/07/2025SfP 24/25
BilboroughGlaisdale DrivePlanned Patching On site Summer 2025SfP 24/25
BilboroughHucknall RoadMicro AsphaltProgrammed04/08/2025LTP 24/25
BilboroughRosedale DriveMicro AsphaltComplete23/03/2025LTP 25/26
BilboroughStrelley RoadResurfaceComplete17/02/2025LTP 24/25
BilboroughWollaton ValeFootway ResurfaceProgrammed04/08/2025SfP 24/25
BilboroughWoodhouse WayResurfaceComplete06/05/2025SfP 24/25
BilboroughWoodhouse WayReconstructionIn DevelopmentTo Be ConfirmedLTP 25/26
BulwellArmstrong RoadMicro AsphaltComplete22/03/2025SfP 24/25
BulwellHazel StreetMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
BulwellLime Street / Muriel StreetResurfaceComplete29/11/2024SfP 24/25
BulwellMerchant StreetMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
BulwellMinerva StreetMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
BulwellSquires AvenueResurfaceComplete07/04/2025SfP 24/25
BulwellSquires AvenueResurfaceComplete02/04/2025SfP 24/25
BulwellWard wide Planned PatchingComplete01/12/2024SfP 24/25
Bulwell ForestBelmont Avenue Retread Complete26/03/2025SfP 24/25
Bulwell ForestBestwood Road Retread Complete27/03/2025SfP 24/25
Bulwell ForestBrora RoadMicro AsphaltComplete16/04/2024LTP 24/25
Bulwell ForestPiccadillyPlanned PatchingComplete01/02/2025SfP 24/25
Bulwell ForestRidgewayResurfaceComplete03/03/2025SfP 24/25
Bulwell ForestShakespeare StreetReconstructionProgrammed04/08/2025LTP 24/25
Bulwell ForestSt Albans Road ResurfaceProgrammed28/07/2025SfP 24/25
Bulwell ForestTorkard Drive/Old Farm RoadDropped Crossing ImprovementsIn DevelopmentSummer 2025SfP 24/25
Bulwell ForestWard Wide Planned PatchingIn DevelopmentSummer 2025SfP 24/25
CastleClumber StreetResurfacingProgrammed04/08/2025LTP 24/25
CastleNuthall RoadResurfacingProgrammed07/07/2025LTP 24/25
CastleOld Lenton StreetJunction RealignmentIn DevelopmentSummer 2025SfP 24/25
CastlePlumptre StreetResurfaceComplete10/03/2025SfP 24/25
CastleSt James's TerraceResurfaceComplete15/03/2025SfP 24/25
CastleWard Wide Bin ReplacementCompleteSummer 2025SfP 24/25
CastleWard Wide New Trees/Urban Greening Part Complete Summer 2025SfP 24/25
Clifton EastBlaise CloseMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
Clifton EastCaister RoadMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
Clifton EastCerne CloseMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
Clifton EastClifton LaneResurfaceProgrammed21/07/2025SfP 24/25
Clifton EastDungannon RoadResurfaceComplete07/04/2025SfP 24/25
Clifton EastFarnborough RoadRaised Plateau ResurfacingProgrammed23/06/2025SfP 24/25
Clifton EastGreencroft AreaResidents Parking SchemeIn DevelopmentSummer 2025SfP 24/25
Clifton EastMiddlefell WaySlurry SealComplete18/03/2025SfP 24/25
Clifton EastOldoak RoadResurfaceComplete22/11/2024SfP 24/25
Clifton EastWard wide Bin ReplacementPart Complete Summer 2025SfP 24/25
Clifton EastWoodkirk RoadReconstructionIn DevelopmentTo Be ConfirmedLTP 25/26
Clifton EastWrenthorpe ValeMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
Clifton NorthRuddington LaneMicro AsphaltComplete21/04/2024LTP 24/25
Clifton WestAaron CloseMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
Clifton WestBader RoadMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
Clifton WestBrookthorpe WayMicro AsphaltComplete19/03/2025SfP 24/25
Clifton WestCribb CloseMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
Clifton WestHannah CrescentMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
Clifton WestHolgateRetreadComplete26/03/2025SfP 24/25
Clifton WestPieris DriveMicro AsphaltComplete18/03/2025SfP 24/25
Clifton WestVillage RoadRetreadComplete26/03/2025LTP 24/25
DalesAvon RoadReconstructionIn DevelopmentTo Be ConfirmedEMCCA 25/26
DalesBewick DriveMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
DalesBewick Drive AreaDropped Crossing ImprovementsIn DevelopmentSummer 2025SfP 24/25
DalesCardale RoadResurfaceComplete19/08/2024LTP 24/25
DalesDaleside RoadMicro AsphaltIn DevelopmentTo Be ConfirmedLTP 25/26
DalesDaleview RoadRetreadComplete31/03/2025SfP 24/25
DalesHereford RoadRetreadComplete24/03/2025SfP 24/25
DalesHereford RoadResurfaceProgrammed24/07/2025SfP 24/25
HGAA610 Bobbers Mill Bridge Road Safety Improvements In DevelopmentSummer 2025SfP 24/25
HGABentinck RoadResurfaceComplete07/10/2024LTP 24/25
HGAColville StreetReconstructionIn DevelopmentTo Be ConfirmedLTP 25/26
HGADarley Road and Darley Avenue Micro AsphaltComplete17/03/2025SfP 24/25
HGADundas CloseMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
HGAGill Street and Hampden Street Dropped Crossing ImprovementsIn DevelopmentSummer 2025SfP 24/25
HGAHampden StreetMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
HGAIreton StreetMicro AsphaltComplete06/04/2024LTP 24/25
HGAKnighton AvenueMicro AsphaltComplete25/03/2025SfP 24/25
HGANewstead GroveResurfaceComplete27/01/2025SfP 24/25
HGAWard Wide Planned Patching Complete12/12/2024SfP 24/25
HGAWard Wide Bin ReplacementIn DevelopmentSummer 2025SfP 24/25
Leen ValleyAspley LaneMicro AsphaltComplete18/04/2024LTP 24/25
Leen ValleyBeechdale RoadHFSComplete01/11/2024LTP 24/25
Leen ValleyBexleigh GardensMicro AsphaltComplete25/03/2025LTP 25/26
Leen ValleyHolbeck RoadResurfaceComplete01/11/2024LTP 24/25
Leen ValleyTrentham DriveResurfaceComplete20/03/2025SfP 24/25
Leen ValleyWard Wide Bin ReplacementIn DevelopmentSummer 2025SfP 24/25
Leen ValleyWard Wide Planned Patching Complete01/12/2024SfP 24/25
Leen ValleyWestern BoulevardResurfacingProgrammed07/07/2025LTP 24/25
Leen ValleyWilford Crescent EastResurfacingIn DevelopmentTo Be ConfirmedLTP 24/25
Leen ValleyWilkinson StreetResurfaceComplete23/09/2024LTP 24/25
LWEBroughton Drive/Austrey AvenueParking Restrictions In DevelopmentSummer 2025SfP 24/25
LWEGregory StreetMicro AsphaltComplete20/04/2024LTP 24/25
LWEHawton CrescentResurfaceComplete07/04/2025SfP 24/25
LWELenton LaneMicro AsphaltComplete02/04/2024LTP 24/25
LWENewland CloseResurfaceComplete14/03/2025SfP 24/25
LWEScalford DriveMicro AsphaltComplete21/03/2025SfP 24/25
LWESelston DriveRetreadComplete26/03/2025LTP 25/26
LWETrinity Avenue / Church Avenue / Albert Road / Lois AvenueMicro AsphaltComplete22/03/2025SfP 24/25
MapperleyBoynton RoadMicro AsphaltComplete23/03/2025SfP 24/25
MapperleyBrewsters Road ResurfaceComplete24/02/2025SfP 24/25
MapperleyDagmar GroveMicro AsphaltComplete04/04/2024LTP 24/25
MapperleyEaton StreetMicro AsphaltComplete23/03/2025SfP 24/25
MapperleyMapperley Hall DriveRetreadComplete01/04/2025LTP 25/26
MapperleyMapperley RiseMicro AsphaltComplete03/04/2024LTP 24/25
MapperleyMapperley RoadMicro AsphaltComplete04/04/2024LTP 24/25
MapperleySpringwood GardensRetreadComplete25/03/2025LTP 24/25
MapperleyWoodlane GardensMicro AsphaltComplete23/03/2025SfP 24/25
MeadowsArleston DriveResurfacingProgrammed11/08/2025LTP 24/25
MeadowsBathley StreetResurfaceComplete11/03/2025SfP 24/25
MeadowsBathley StreetSlurry SealComplete04/03/2025SfP 24/25
MeadowsBeardsley GardensMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
MeadowsBunbury StreetMicro AsphaltComplete21/03/2025SfP 24/25
MeadowsBurge CloseMicro AsphaltComplete21/03/2025SfP 24/25
MeadowsColliery Close Surfacing and Drainage Improvements Live02/06/2025SfP 24/25
MeadowsKelso GardensMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
MeadowsQuayside Close/ Meadows Close and Beauvale Road Residents Parking SchemeIn DevelopmentSummer 2025SfP 24/25
MeadowsQueens Drive (Phase 3)ResurfacingIn DevelopmentTo Be ConfirmedLTP 25/26
MeadowsQueens Drive (Phase 1)ResurfaceComplete09/09/2024LTP 24/25
MeadowsQueens Drive (Phase 2)ResurfaceComplete04/11/2024LTP 24/25
MeadowsQueen's Road New Pedestrian Crossing Programmed 28/07/2025SfP 24/25
MeadowsRobin Hood WayFootpath Improvements In DevelopmentTo Be ConfirmedSfP 24/25
MeadowsSaffron GardensMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
MeadowsSt Georges DriveMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
RadfordArgyle StreetMicro AsphaltComplete24/03/2025SfP 24/25
RadfordBalfour RoadResurfaceComplete10/03/2025SfP 24/25
RadfordBastion StreetResurfacingIn DevelopmentTo Be ConfirmedLTP 25/26
RadfordBovill StreetMicro AsphaltComplete26/03/2025LTP 25/26
RadfordBright StreetMicro AsphaltComplete08/04/2024LTP 24/25
RadfordDorking RoadMicro AsphaltComplete25/03/2025LTP 25/26
RadfordDouglas RoadResurfaceComplete24/03/2025SfP 24/25
RadfordFaraday RoadMicro AsphaltComplete10/04/2024LTP 24/25
RadfordGarden StreetMicro AsphaltComplete07/04/2024LTP 24/25
RadfordGraham StreetMicro AsphaltComplete08/04/2024EMCCA 25/26
RadfordMiall StreetMicro AsphaltComplete08/04/2024LTP 24/25
RadfordMiddleton StreetMicro AsphaltComplete09/04/2024LTP 24/25
RadfordNorton StreetMicro AsphaltComplete22/03/2025SfP 24/25
RadfordSalisbury SquareMicro AsphaltComplete09/04/2024LTP 24/25
RadfordSalisbury StreetMicro AsphaltComplete09/04/2024LTP 24/25
RadfordWard Wide Bin ReplacementIn DevelopmentSummer 2025SfP 24/25
RadfordWellington SquareMicro AsphaltComplete06/04/2024LTP 24/25
SherwoodA6514 Valley RoadMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
SherwoodAmpthill RiseMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
SherwoodLongdale DriveResurfaceComplete12/08/2024LTP 24/25
SherwoodLoscoe Road CyclewayComplete01/04/2025SfP 24/25
SherwoodMansfield Rd Area Residents Parking and Car Parks Scheme In DevelopmentSummer 2025SfP 24/25
SherwoodPerry RoadReconstructionIn DevelopmentTo Be ConfirmedLTP 25/26
SherwoodPerry Road Planned Patching On site 31/01/2025SfP 24/25
SherwoodRaven AvenueMicro AsphaltIn DevelopmentTo Be ConfirmedEMCCA 25/26
SherwoodWard Wide Bin ReplacementIn DevelopmentSummer 2025SfP 24/25
SherwoodWhatton Rise / Bradmore RiseResurfaceComplete06/01/2025SfP 24/25
SherwoodWinchester Street CyclewayPart Complete Summer 2025SfP 24/25
St Ann'sCardinal CloseResurfaceComplete13/12/2024SfP 24/25
St Ann'sConway Close ResurfaceComplete10/03/2025SfP 24/25
St Ann'sKilbourn StreetResurfaceComplete10/03/2025SfP 24/25
St Ann'sLotus CloseMicro AsphaltComplete24/03/2025SfP 24/25
St Ann'sRobin Hood StreetResurfaceComplete22/04/2025SfP 24/25
St Ann'sSherwin Walk Highway ImprovementsLive02/06/2025SfP 24/25
St Ann'sTeak CloseResurfaceComplete18/12/2024SfP 24/25
St Ann'sWard Wide Bin ReplacementIn DevelopmentSummer 2025SfP 24/25
St. AnnsCarlton RoadMicro AsphaltComplete02/04/2024LTP 24/25
St. AnnsLower Parliament StreetResurfaceComplete01/08/2024LTP 24/25
Wollaton WestDovecote DriveMicro AsphaltComplete17/04/2024LTP 24/25
Wollaton WestGrangewood RoadMicro AsphaltComplete25/03/2025LTP 24/25
Wollaton WestGrangewood RoadMicro AsphaltIn DevelopmentTo Be ConfirmedLTP 25/26
Wollaton WestRenfrew DriveRetreadComplete03/04/2025SfP 24/25
Wollaton WestRussell AvenueRetreadComplete28/03/2025LTP 25/26
Wollaton WestSmithson DriveMicro AsphaltComplete17/04/2024LTP 24/25
Wollaton WestWard Wide Bin ReplacementIn DevelopmentSummer 2025SfP 24/25
Wollaton WestWollaton Road ResurfaceComplete12/05/2025SfP 24/25
Wollaton WestWollaton Road (Access Road)Micro AsphaltComplete15/04/2024LTP 24/25