Overnight closures to London Road Island and Lower Parliament Street

Roadworks sign

Nottingham City Council has been working to build the cross city cycle route – connecting the Western Cycle Corridor (along Castle Boulevard) and the Eastern Cycle Corridor (along Daleside Road) with a high quality segregated cycle path. The central section – along London Road and Fisher Gate is nearly complete. The final stage of this project will see road resurfacing works on London Road Roundabout, Lower Parliament Street, Hollow Stone and Fisher Gate.

These works are funded by a government grant as part of the Transforming Cities Fund – a pot of money aimed at promoting sustainable transport methods and connecting people with employment opportunities.

Works start on the night of Sunday 7 April 2024 and will take place overnight Monday to Friday 10pm to 6am for four weeks. Road closures will be in place with signed diversions.

Given the location of the works – Nottingham City Council has been working closely with the Motorpoint Arena to ensure that road closures will not have significant impacts on people leaving the arena. On nights when there are events finishing later in the evening, road closures will start at 11pm so as to ensure concert goers have left the area.

Councillor Angela Kandola, Nottingham City Council’s portfolio holder for transport said, “The cross city cycle route is nearing completion and it’s an exciting time for this project. We are working hard to minimise disruption as we move into the final phase. Our crews have worked hard to schedule multiple projects in the area at the same time to work more efficiently and minimise disruption and will be working overnight as they resurface this busy junction. There will be significant diversions in place so if you are travelling in the area between 10pm and 6am allow extra time for your journey.”

Works detail;

Phase 1 – Sunday 7 April – Tuesday 16 April 8 nights

Resurfacing of north, south and west side of BBC Roundabout, London Road and Hollow Stone.

During phase 1a, London Road northbound will be closed from its junction with Queen’s Road to Hollow Stone. There will be no access into and out of Canal Street and no exit from Station Street onto London Road. Download a pdf copy of the diversion plan for this here.

During phase 1b, London Road northbound will be closed from BBC Roundabout to Hollow Stone. Download a pdf copy of the diversion plan for this here.

Phase 2 –Wednesday 17 April – Monday 29 April 9 nights

Resurfacing of Lower Parliament Street, from its junction with Pennyfoot Street/Fisher Gate to the London Road/City Link junction including the east side of BBC Roundabout.

Lower Parliament Street will be closed from its junction with Southwell Road to London Road just south of its junction with City Link.  Download a copy of the map below here.

Phase 3 – Nights of Tuesday 30 April – Wednesday 1 May 2 nights

Resurfacing of Fisher Gate between Hollow Stone and Lower Parliament Street.

Fisher Gate will be closed between Hollow Stone and Lower Parliament Street. There will be lane closures on Lower Parliament Street, Hollow Stone and around BBC roundabout.

Day-time Lane Closures

During the works, there will be lane closures during the daytime. These will be limited to one lane and only in place for one day to protect the new surfacing joints, to ensure the longevity of the new surface. Access to properties will be maintained.