Here you can find the most up to date information on our live highway maintenance schemes.
Nuthall Road Tree Pit Improvements to Footway (Llanberis Grove to Western Boulevard)
| Scheme Detail | Footway Improvements |
| Restrictions | Localised TM & Lane Closures |
| Start Date | 19/10/2026 |
| Duration | 4 Weeks |
| Contractor | Trust - 0115 9309325 |
London Road Gateway – Maintenance and Greening Improvements
| Scheme Detail | London Road Gateway - Maintenance & Greening Improvements |
| Restrictions | Lane Closures |
| Start Date | 13/07/2026 |
| Duration | Phase 2 - 17 Weeks |
| Contractor | Nottingham City Council - 0115 9152000 |
| Further Information | London Road Phase 2 letter |
Hoewood Road Bridge Railings Replacement
| Scheme Detail | Bridge Railings Replacement |
| Restrictions | 2-way lights |
| Start Date | 13/07/2026 |
| Duration | 12 weeks |
| Contractor | Danaher and Walsh |
| Additional Info | Hoewood Road letter |
Nuthall Road (Western Boulevard to Aspley Lane)
| Scheme Detail | Carriageway Resurfacing |
| Restrictions | Lane closures and inbound and outbound road closures |
| Start Date | 29/06/2026 |
| Duration | 8 weeks |
| Contractor | Thomas Bow - 0115 9244555 |
| Further Information | Nuthall Rd letter 26 08 26 |
Bramcote Lane (Renfrew Drive to Wollaton Road)
| Scheme Detail | Carriageway Resurfacing |
| Restrictions | Road Closure |
| Start Date | 3/8/2026 |
| Duration | 7 weeks |
| Contractor | Thomas Bow |
| Additional Info | Bramcote Lane letter 23 7 26 |
Abbey Bridge/Abbey Street and Gregory St junction with Leen Gate
| Scheme Detail | Carriageway Resurfacing |
| Restrictions | Road Closure 7pm to 6am |
| Start Date | 17th August |
| Duration | 2.5 weeks |
| Contractor | RPH (01623 238432) |
| Additional Information | Abbey Bridge letter 29 7 26 |
Robin Hood Way – Bus stop, footway and resurfacing improvements
| Scheme Detail | Bus stop, footway and resurfacing improvements |
| Restrictions | Temporary lights from 17th Aug and road closure from 1st to 4th Sept 9.30am-3.30pm |
| Start Date | 17/8/2026 |
| Duration | 3 weeks |
| Contractor | Trust 0115 9309325 |
| Further Information | Robin Hood Way letter 3 8 26 |
Beeston Road
| Scheme Detail | Carriageway Resurfacing |
| Restrictions | Road Closure 7pm to 6am |
| Start Date | 7th September |
| Duration | 2 weeks |
| Contractor | RPH (01623 238432) |
| Additional Information | Beeston Rd letter and plan 24 8 26 |
Nuthall Road (Cinderhill Island to Llanberis Grove)
| Scheme Detail | Carriageway Resurfacing |
| Restrictions | Lane closures and inbound and outbound road closures |
| Start Date | 14 September |
| Duration | 5 weeks |
| Contractor | Thomas Bow - 0115 9244555 |
| Further Information | Nuthall Road - Cinderhill to Llanberis letter & plan 27 8 26 |
Hucknall Road (Bestwood Road to Aldi)
| Scheme Detail | Microsurfacing |
| Start Date | 14th September |
| Duration | 1.5 weeks |
| Contractor | Colas |
| Carriageway Restrictions | Phased road closure |
| Further Information | Hucknall Rd letter and plan 3 9 26 |
Microsurfacing Programme
| Scheme Detail | Microsurfacing |
| Restrictions | Road Closures |
| Start Date | 02/09/2026 |
| Duration | 1 week |
| Contractor | Kiely Group tel: 0121 772 3800 |
| Further Information | Micro Schemes Programme 4 Sept 2026 |