Here you can find the most up to date information on our live highway maintenance schemes.
Nuthall Road Area
Scheme Detail | Carriageway resurfacing |
Restrictions | Road Closures |
Start Date | 07/07/2025 |
Duration | 8 Weeks |
Contractor | Thomas Bow - 0115 924 4555 |
Additional Information | Nuthall Road Area |
Arleston Drive
Scheme Detail | Carriageway Resurfacing |
Start Date | 14/07/2025 |
Duration | 7 Weeks |
Contractor | Thomas Bow - 0115 924 4555 |
Footway Restrictions | Localised traffic management 14th July to 1st August |
Carriageway Restrictions | Road Closure 4th to 28th August (0800-1700) |
Additional Information | Arleston Drive |
Bracebridge Drive
Scheme Detail | Carriageway Resurfacing |
Restrictions | Road Closure |
Start Date | 28/07/2025 |
Duration | 5 Weeks |
Contractor | Miles Macadam 01948 820489 |
Southglade Road
Scheme Detail | Carriageway resurfacing |
Restrictions | Road Closure |
Start Date | 28/07/2025 |
Duration | 4 Weeks |
Contractor | Hanson 0333 009 8407 |
Additional Information | Southglade Road |
Dungannon Road
Scheme Detail | Carriageway resurfacing |
Restrictions | Road Closure |
Start Date | 30/07/2025 |
Duration | 3 Weeks |
Contractor | Tarmac 0116 2648540 |
Micro Asphalt Programme
Scheme Detail | Carriageway Surface Treatment |
Restrictions | Road Closures & Lane Closures |
Start Date | 08/08/2025 |
Duration | 4 Weeks |
Contractor | Colas - 01476 404200 |
Programme Information | Micro Asphalt Programme |
Chingford Road
Scheme Detail | Carriageway Resurfacing |
Restrictions | Road Closure |
Start Date | 14/08/2025 |
Duration | 1 Week |
Contractor | Miles Macadam 01948 820489 |
St Albans Road
Scheme Detail | Carriageway resurfacing |
Restrictions | Road Closure |
Start Date | 18/08/2025 |
Duration | 1 Week |
Contractor | Hanson 0333 009 8407 |
Additional Information | St Albans Road |
Shakespeare Street
Scheme Detail | Carriageway Resurfacing |
Restrictions | Night Road Closure |
Start Date | 26/08/2025 |
Duration | 2 Weeks |
Contractor | RPH 01623 238432 |
Additional Information | Shakespeare Street Letter |
Lady Bay Bridge
Scheme Detail | Bridge Repainting |
Start Date | 16/06/2025 |
Duration | 17 Weeks |
Contractor | Dart Industrial Services Ltd - 01325 498 175 |
Footway Restrictions | Footway Closures between 7th July to 20th August (0830 to 1730) |
Carriageway Restrictions | Night Time Road Closures between 7th July to 17th August (2000 to 0600) |