St Ann's Well Road, St Ann's
- Start: 5 June 2023
- End: 15 August 2023
What's happening?
From 5 June until 20 June 2023, we will be undertaking works to narrow the junction of St Ann’s Valley / St Ann’s Well Road (the one adjacent to Heron Food).
Thereafter the work will involve the removal and replacement of three existing raised crossings, which are in a poor state of repair. For each crossing we will close the road for one day on a Sunday to enable the new raised crossing to be built. A signed diversion route will be in place on these days.
St Anns Well Road Diversion plan
All other work will be undertaken using traffic management on a single running lane on the approach / exit from each crossing will be maintained to minimise disruption to road users although please expect some delays.
Zebra No.1 – Located on St Ann’s Well Road in vicinity of Luther Close / St Ann’s Valley junction
- Start date: 20th June
- Road closure date: 2nd July (all day)
- Info: between 20th June and 4th July, kerbing works and work to remove the raised zebra (one side at a time) will take place using signal controlled traffic management to take on lane out at a time when necessary.
- Total duration of works: 2 weeks
Zebra No.2 – Located at the end of Robin Hood Chase and between St Ann’s Police Station and the Post Office
- Start date: 4th July
- Road closure date: 16th July (all day)
- Info: between 4th July and 18th July, kerbing works and work to remove the raised zebra (one side at a time) will take place using signal controlled traffic management to take on lane out at a time when necessary.
- Total duration of works: 2 weeks
Zebra No.3 – Located adjacent to the Depot Climbing Centre and adjacent to the roundabout junction of Bath Street / Beck Street etc
- Start date: 18th July
- Road closure date: 13th August (all day)
- Info: between 18th July and 15th August, kerbing works and work to remove the raised zebra (one side at a time) will take place using signal controlled traffic management to take on lane out at a time when necessary.
- Total duration of works: 4 weeks