If you have received a PCN for the Canal Street bus gate during the overnight works, this was issued in error and will be cancelled – no action is required.

Phase 1

Phase 1 – Sunday 7 April – Tuesday 16 April 8 nights

Resurfacing of north, south and west side of BBC Roundabout, London Road and Hollow Stone.

During phase 1a, London Road northbound will be closed from its junction with Queen’s Road to Hollow Stone. There will be no access into and out of Canal Street and no exit from Station Street onto London Road. Download a pdf copy of the diversion plan for this here.

During phase 1b, London Road northbound will be closed from BBC Roundabout to Hollow Stone. Download a pdf copy of the diversion plan for this here.

 

Phase 2

Phase 2 –Wednesday 17 April – Monday 29 April 9 nights

Resurfacing of Lower Parliament Street, from its junction with Pennyfoot Street/Fisher Gate to the London Road/City Link junction including the east side of BBC Roundabout.

Lower Parliament Street will be closed from its junction with Southwell Road to London Road just south of its junction with City Link. Download a copy of the map below here.

 

Phase 3

Phase 3 – Nights of Tuesday 30 April – Wednesday 1 May 2 nights

Resurfacing of Fisher Gate between Hollow Stone and Lower Parliament Street.

Fisher Gate will be closed between Hollow Stone and Lower Parliament Street. There will be lane closures on Lower Parliament Street, Hollow Stone and around BBC roundabout.

Daytime road closures

During the works, there will be lane closures during the daytime. These will be limited to one lane and only in place for one day to protect the new surfacing joints, to ensure the longevity of the new surface. Access to properties will be maintained.