Latest Updates

If programme works are affected by weather or other delays we will update you here. Please use the bar at the bottom of the table to see all the details.

Road name Scheme detail Restrictions Start date Duration Contractor
Arnold Road Island Cycleway Improvement & Footway Resurfacing Localised footway closures 22/01/2024 14 weeks Trust
Burns Street Footway resurfacing Footway closure 05/02/2024 12 weeks Trust
Brora Road Carriageway Micro Asphalt Road Closure 15/04/2024 1 week Colas
Lytham Gardens Carriageway Micro Asphalt Road Closure 16/04/2024 1 week Colas
Smithson Drive Carriageway Micro Asphalt Road Closure 18/04/2024 1 week Colas
Aspley Lane Carriageway Micro Asphalt Road Closure 18/04/2024 1 week Colas
Ruddington Lane Carriageway Micro Asphalt Road Closure 21/04/2024 1 week Colas
Gregory Street Carriageway Micro Asphalt Road Closure 22/04/2024 1 week Colas
Mount Pleasant Carriageway Micro Asphalt Road Closure TBC 1 week Colas
Marlow Avenue Carriageway Micro Asphalt Road Closure TBC 1 week Colas